For most of 2026, the Campbells Run Road project has looked like any other summer road job: flaggers, one lane open, a few extra minutes between Keiners Lane and McMichael Road. That stage runs through the end of this year. After that, the county's plan works differently. Eastbound, inbound travel stays open for the whole project. From 2027 through 2031, different sections of the road close to westbound traffic, one section at a time. If you live in Collier, inbound trips stay roughly the same. Outbound trips are the ones that change, and for months at a time.
The county describes the scope plainly. It is a $45.8 million rebuild and the largest road project Allegheny County's Department of Public Works has ever taken on. It covers a road that became a county road in 1907 and now carries an average of 14,646 vehicles a day, according to Collier Township's project notice. The Federal Highway Administration pays 80% of the cost and the county pays the other 20%. Golden Triangle Construction of Findlay is the main contractor.
Why the Road Closes One Direction at a Time
The design follows from the problem it is meant to fix. More than 50 side streets and driveways open onto the 1.63-mile, two-lane stretch between McMichael Road and Keiners Lane. The worst backup is at Boyce Road. There, westbound drivers have to wait for a gap in eastbound traffic before turning left toward the I-376 East entrance ramp. The offset intersections with Boyce Road and Parkway View Drive, plus the signal at the Exit 62 off-ramp, add to the backup.
According to the county, the project takes five years for four reasons: the scope is large, many utilities have to be moved, much of the work can only happen in warm weather, and the sections have to be built in a set order. That approach keeps the road from closing completely and keeps the homes and businesses along it reachable throughout. Keeping it reachable means keeping one direction open, and the county chose eastbound.
What Is Happening Right Now
On the county's Engage Allegheny project page, the current stage lists stormwater basin construction, the Glass Road culvert extension, drainage work, and moving and upgrading utilities. The culvert extension near the former Outlet Barn was one of the first jobs. The county said it would need short single-lane closures with flaggers, and that utility work on both sides of it would need periodic lane closures too. Duquesne Light told the county it does not expect any power outages near Vesuvius from its relocation work.
This is the easy stretch of the project. Every closure so far has been temporary and run by flaggers.
The Sequence the County Has Published
The project dashboard lists the next stages in order. It gives no dates and marks every stage as subject to change. Read in sequence, the stages work their way along the corridor.
| Listed stage | Westbound closure | Side-road access affected | Main work |
|---|---|---|---|
| Next | Penn Center Boulevard to the I-376 West Exit 62 ramp | Boyce Road, Parkway View Drive | Start of closure-based phases |
| Following | Boyce Road to Vista Drive, and Penn Center Boulevard to Exit 62 | Glass Road, Vista Drive | Roadway reconstruction, retaining walls, signals, Boyce Road culvert replacement, Parkway View Drive realignment |
| Later | Penn Center Boulevard to Sir Speedy at 4573 Campbells Run Road | Keiners Lane | Culvert extension at Keiners Lane |
| Final listed | Keiners Lane to Penn Center Boulevard, and Vista Drive to McMichael Road | None listed | Completion of remaining sections |
The county's 2027 budget document calls next year the project's second year and lists road widening and reconstruction, retaining walls and drainage work.
The Detours Show What a Westbound Closure Means
The county has already named its detours. When a section of westbound Campbells Run Road is closed, traffic will be sent along Mansfield Boulevard, Chestnut Street, Academy Street and I-376. When access at Vista Drive is closed, the detour runs along Parkway View Drive, through the Parkway West Business Park, and out Mar Vista Drive.
The county's answers to individual businesses show what this looks like at specific addresses. Vesuvius, at 4604 Campbells Run Road, is the clearest case. Once the westbound closure in front of it starts, drivers will have to come from the west. The county's example route is the "To Ridge Road" Exit 61 off-ramp from the Parkway West, then a right onto Campbells Run Road heading east. Drivers leaving will have to head east toward Carnegie. The same logic applies to any driveway or side street in a closed section. You can get in from one direction, and you leave the way the open lane runs.
The Parkway West Business Park gets a similar arrangement. While the Vista Drive closure is in place, the county says drivers should reach the park by heading eastbound on Campbells Run Road and turning left onto Parkway View Drive. During the Boyce Road and Parkway View realignment, drivers coming off the I-376 West ramp can reach Parkway View by turning right onto Campbells Run Road and then left onto Glass Road. The county has also told the office at 800 Vista Park Drive that it will have access throughout the project.
How Long Each Closure Lasts Matters More Than When It Starts
The county's own answer about the Vista Drive area explains why 2027 will feel different from this year:
"When those traffic restrictions are implemented, they will be continuous – 24 hours a day, seven days a week – for months."
Flagger closures come and go within a workday. Closures run 24 hours a day for months turn the detour into your normal route for a season.
As of the county's latest published answers, the start date is uncertain. For the westbound closure in front of Vesuvius, the county said it expected a start in early 2027. It also said the contractor had not scheduled that far ahead and that it could not say how long the section would stay closed. For the Vista Drive closures, the county said it had originally planned them for an early phase in 2027 or 2028. It then called that timeline "in flux" because steel for the project's nine retaining walls was delayed. The page doesn't date either reply. The questions are marked as asked several months ago, and the page footer still says it was last updated in March. So early 2027 is the county's tentative estimate, not a firm date.
The county has said how it will announce each change. Before any new restriction starts, it will update the project page, issue a press release, send an Allegheny Alert, and post on social media. Of those four, the Allegheny Alert comes straight to your phone, so it is the easiest way to hear about a closure before it starts.
The Businesses Along the Corridor Have Talked About It
Businesses on this stretch have commented on the project in local news coverage. WTAE's report on opening day included Bishops Corner Cafe at Boyce Road, which sits at the intersection set to be realigned with Parkway View Drive. WPXI reported that Snyder Brothers Auto was weighing how construction could affect customers before the work is done. In the West Hills Gazette, Snyder Brothers' owner said he expects some disruption and a long-term benefit, and ServiceMaster, in a plaza near McMichael Road, raised concerns about traffic being diverted.
Inbound-only access affects these places the same way it affects your driveway. Anyone coming from the east has to go around to arrive, and everyone leaves heading east. If you are a regular at one of these businesses, your route there may change for a season even if theirs does not.
What the Finished Road Adds
When the work is done, the stretch between McMichael Road and Keiners Lane will have:
- A two-way center turn lane, plus left- and right-turn lanes at major intersections
- A new four-way signalized intersection where Boyce Road and Parkway View Drive line up
- A sidewalk between Business Center Drive and Penn Center Boulevard
- A wider I-376 West off-ramp at Exit 62
- Upgraded signals at existing signalized intersections
- New curbs, guide rail, signs and pavement markings, including bike sharrows
The center turn lane is aimed at the problem described earlier: drivers stopped in the travel lane waiting to turn into one of 50-plus driveways and side streets. The new Boyce Road intersection is aimed at the left turn toward the I-376 East ramp, where the county says congestion is worst today. The county's estimated completion year is 2031.
If you are thinking about a sale, a purchase or a lease in Collier and want to know how each westbound closure lines up with a particular street or driveway, The Burgh Luxury can go through the county's published sequence with you. Kristie Martin works from nearby Bridgeville and follows the Campbells Run Road project as each new restriction is announced. Let's Connect.